➤ একটা বিল্ডিং এর সকল আইটেম মিলে ১০০% কিভাবে ভাগ করা হয়।
☞ উত্তরঃ
1. Structure = 35%
2. Brick work = 6%
3. Wood work = 5%
4. Metal work = 2%
5. Plambing and Sanitary = 6%
6. Electrical work = 7%
7. Plaster work = 4%
8. General Floor Tiles work = 6%
9. Toilet & Kit wall Tiles work = 3%
10. Aluminium work = 4%
11. EME(Lift,Generator,Substation)=10%
12. Paint work = 3%
13. Others civil work = 6%
14. Utility connection & Bill = 3%
Total = 100%
✪ STRUCTURE ~ 35%
- Footing & Column Padestal = 20%
- Grade Beam, UGWR top Slab = 5%
- GF Column, Stair etc = 4%
- 1st Floor Slab = 9%
- Typical Floor Column (5x3%) = 15%
- 2nd floor slab to roof slab (5x8) = 40%
- Roof top = 7%
TOTAL = 100% (৩৫% যেভাবে আসবে।)
#সিভিল_ইঞ্জিনিয়ারিং
✪ BRICK WORK ~ 6%
- GF Brick work = 6%
- 1st floor Brick work = 18%
- 2nd floor Brick work = 18%
- 3rd floor Brick work = 18%
- 4th floor Brick work = 18%
- 5th floor Brick work = 18%
-Roof Top Brick work = 4%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ WOOD WORK ~ 5%
- Door frame = 40%
- Main Door Shutter = 15%
- Partex Door Shutter = 35%
- Cat Door & Accessories = 10%
TOTAL = 100% (৫% যেভাবে হবে)
✪ METAL WORK ~ 2%
- Window grill = 55%
- Verandah Railling = 20%
- Stair Railling = 10%
- Main gate, Gen-Sub, safety grill = 15%
TOTAL = 100% (২% যেভাবে হবে।)
✪ PLAMBING & SANITARY WORK~ 6%
- uPVC vertical line thru duct = 25%
- GI line work = 30%
- Fixture & Fittings = 40%
- Ground Floor = 5%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ ELECTRICAL~ 7%
- Conduiting inside slab = 10%
- Conduiting on wall i/c MK box=15%
- Cabling work = 55%
- Switch-Socket = 20%
TOTAL = 100% (৭% যেভাবে হবে।)
✪ PLASTER ~ 4%
- Ceiling plaster = 20%
- Internal wall plaster = 50%
- Outside plaster/facing bricks = 30%
TOTAL = 100% (৪% যেভাবে হবে।)
✪ GENERAL FLOOR TILES ~ 6%
- General floor & Verandah = 75%
- Stair, typical lobby & lift wall = 20%
- GF lift lobby, wall, reception = 5%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ TOILET & KIT WALL TILES ~ 3%
- Bath wall = 60%
- Kitchen wall = 20%
- Bath floor = 9%
- Bath counter top = 4%
- Kitchen floor = 3%
- Kitchen counter top =4%
TOTAL = 100% (৩% যেভাবে হবে।)
✪ ALUMINIUM WORK ~ 4%
- Outer framing-window sliding= 40%
- Glass shutter-window sliding = 30%
- Verandah sliding = 20%
- Toilet high window = 5%
- Comnon area = 5%
TOTAL = 100% (৪% যেভাবে হবে।)
✪ EME ~ 10%
- Lift = 50%
- Generator = 25%
- Substation = 20%
- PABX, Fire extinguisher etc = 5%
TOTAL = 100% (১০% যেভাবে হবে।)
✪ PAINT WORK ~ 3%
- Upto putty = 40%
- Internal wall&ceiling 1st coat= 20%
- Internal wall&ceiling 2nd coat= 15%
- Outside paint/ceramic Tites = 25%
TOTAL = 100% (৩% যেভাবে হবে।)
সিভিল ইঞ্জিনিয়ারিং
✪ OTHERS CIVIL WORK ~ 6%
- Boundary wall = 30%
- Line terracing/Roof top paver= 15%
- LOGO, Gardening & others = 4%
- GF BBC = 14%
- GF pavement & footpath dev = 10%
- Lintel, F/slab, drop wall, counter slab = 20%
- Cable tray = 1%
- Sanitary duct cover, ceiling etc= 4%
- Reception desk, letter box = 2%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ UTILITY CONNECTION & BILL ~ 3%
- DESA/DESCO = 35%
- TITAS = 20
- WASA = 15%
- Utility bills = 30%
TOTAL = 100% (৩% যেভাবে হবে।)

06/03/2023

★★★নির্মান কাজে ব্যবহৃত বিভিন্ন সামগ্রীর একক ওজন :-

১। সাধারন কংক্রিট (Plain Concrete)= 2300 kg/m3

২। লোহা যুক্ত কংক্রিট(Reinforced Concrete)= 2400 kg/m3

৩। চুনা কংক্রিট(Lime Concrete)= 1920 kg/m3

৪। সিমেন্ট কংক্রিট(Cement Concrete)= 2240. kg/m3

৫। সিমেন্ট(Cement)= 1440. kg/m3

৬। ইট(Brick)= 1110. kg/m3

৭। ইটের খোয়া(Brick Ballast)= 1200. kg/m3

৮। পাথরকুচি(Stone Ballast)= 1600. kg/m3

৯। ইটের গাঁথুনি(Brick Masonary)= 1920. kg/m3

১০। পাথরের গাথনি(Stone Masonary)= 2560. kg/m3

১১। চুনাপাথর(Linestone)= 2400. kg/m3

১২। চুনা মসলা(Lime mortar)= 1760. kg/m3

১৩। বালি পাথর(Sand Stone)= 2240. kg/m3

১৪। সিমেন্ট মসলা(Cement Mortar)= 1920. kg/m3

১৫। জিপসাম মসলা(Gypsum mortar)= 1200. kg/m3

১৬। পানি(Water at 40'C)= 1000. kg/m3

১৭। এম.এস.রড(M.S.Rods)= 7750-7850. kg/m3

১৮। চুন(Slaked Lime)= 640-960. kg/m3

১৯। কয়লা(Coal)= 900-1280. kg/m3

২০। শুষ্ক বালি(Dry Sand)= 1600-1920. kg/m3

২১। শুষ্ক কাদা(Dry Clay)= 1760-1920. kg/m3

২২। ইট ভাংগা(Broken Bricks)= 1280-1760. kg/m3

২৩।সুরকি(Surki)= 1010-1250. kg/m3

২৪। টার(Tar)= 1010. kg/m3

২৫। মার্বেল(Marble)= 2560. kg/m3

২৬। ঢিলা ও শুকনা মাটি(Loose & Dry earth)= 1440. kg/m3

২৭। মাটি ভরাট(Compacted & Damp earth)= 1600. kg/m3

২৮। বিটুমিন(Bitumen)= 1040. kg/m3

২৯। কোক কয়লা(Coke)= 500. kg/m3

৩০। টালি(Tiles)= 48-65. kg/m3

৩১। সি আই শিট(C.I.Sheet)= 7-12. kg/m3

৩২। হার্ডবোর্ড(Hardboard 12mm thick)= 7. kg/m3

09/07/2022

মার্ক ইঞ্জিনিয়ারিং কোম্পানির পক্ষ থেকে সবাইকে ঈদ মোবারক।

Want your business to be the top-listed Business in Dhaka?
Click here to claim your Sponsored Listing.

Telephone

Website

Address


Komlapur
Dhaka
1212

Opening Hours

Monday 09:00 - 17:00
Tuesday 09:00 - 17:00
Wednesday 09:00 - 17:00
Thursday 09:00 - 17:00
Saturday 09:00 - 17:00
Sunday 09:00 - 17:00