Gazi Joynal Busness, Abdul Alim, Md Shanto Hossain, Arif Hossain, Md Shohel Rana, Md Yeamin Miya, Md. Ail Mohid, TK Tareq Khan, Md Shawon Shawon, Shakib Khan, Arman Sazzad, শিশির ভেজা, Yasin Khan, Md Rahat Hasan Robin, Roy Kazol SK, Suzon Rana, Md Kawser Hossen, Nahid Miah, Mostafijur Rohman Babu, Rafia Ahmed Emon, MD Abdullah Al Noman, Arifuzzaman Arif, Md Raju Islam, Md Obaydul

28/09/2023

➤ একটা বিল্ডিং এর সকল আইটেম মিলে ১০০% কিভাবে ভাগ করা হয়।
☞ উত্তরঃ
1. Structure = 35%
2. Brick work = 6%
3. Wood work = 5%
4. Metal work = 2%
5. Plambing and Sanitary = 6%
6. Electrical work = 7%
7. Plaster work = 4%
8. General Floor Tiles work = 6%
9. Toilet & Kit wall Tiles work = 3%
10. Aluminium work = 4%
11. EME(Lift,Generator,Substation)=10%
12. Paint work = 3%
13. Others civil work = 6%
14. Utility connection & Bill = 3%
Total = 100%
✪ STRUCTURE ~ 35%
- Footing & Column Padestal = 20%
- Grade Beam, UGWR top Slab = 5%
- GF Column, Stair etc = 4%
- 1st Floor Slab = 9%
- Typical Floor Column (5x3%) = 15%
- 2nd floor slab to roof slab (5x8) = 40%
- Roof top = 7%
TOTAL = 100% (৩৫% যেভাবে আসবে।)
#সিভিল_ইঞ্জিনিয়ারিং
✪ BRICK WORK ~ 6%
- GF Brick work = 6%
- 1st floor Brick work = 18%
- 2nd floor Brick work = 18%
- 3rd floor Brick work = 18%
- 4th floor Brick work = 18%
- 5th floor Brick work = 18%
-Roof Top Brick work = 4%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ WOOD WORK ~ 5%
- Door frame = 40%
- Main Door Shutter = 15%
- Partex Door Shutter = 35%
- Cat Door & Accessories = 10%
TOTAL = 100% (৫% যেভাবে হবে)
✪ METAL WORK ~ 2%
- Window grill = 55%
- Verandah Railling = 20%
- Stair Railling = 10%
- Main gate, Gen-Sub, safety grill = 15%
TOTAL = 100% (২% যেভাবে হবে।)
✪ PLAMBING & SANITARY WORK~ 6%
- uPVC vertical line thru duct = 25%
- GI line work = 30%
- Fixture & Fittings = 40%
- Ground Floor = 5%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ ELECTRICAL~ 7%
- Conduiting inside slab = 10%
- Conduiting on wall i/c MK box=15%
- Cabling work = 55%
- Switch-Socket = 20%
TOTAL = 100% (৭% যেভাবে হবে।)
✪ PLASTER ~ 4%
- Ceiling plaster = 20%
- Internal wall plaster = 50%
- Outside plaster/facing bricks = 30%
TOTAL = 100% (৪% যেভাবে হবে।)
✪ GENERAL FLOOR TILES ~ 6%
- General floor & Verandah = 75%
- Stair, typical lobby & lift wall = 20%
- GF lift lobby, wall, reception = 5%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ TOILET & KIT WALL TILES ~ 3%
- Bath wall = 60%
- Kitchen wall = 20%
- Bath floor = 9%
- Bath counter top = 4%
- Kitchen floor = 3%
- Kitchen counter top =4%
TOTAL = 100% (৩% যেভাবে হবে।)
✪ ALUMINIUM WORK ~ 4%
- Outer framing-window sliding= 40%
- Glass shutter-window sliding = 30%
- Verandah sliding = 20%
- Toilet high window = 5%
- Comnon area = 5%
TOTAL = 100% (৪% যেভাবে হবে।)
✪ EME ~ 10%
- Lift = 50%
- Generator = 25%
- Substation = 20%
- PABX, Fire extinguisher etc = 5%
TOTAL = 100% (১০% যেভাবে হবে।)
✪ PAINT WORK ~ 3%
- Upto putty = 40%
- Internal wall&ceiling 1st coat= 20%
- Internal wall&ceiling 2nd coat= 15%
- Outside paint/ceramic Tites = 25%
TOTAL = 100% (৩% যেভাবে হবে।)
সিভিল ইঞ্জিনিয়ারিং
✪ OTHERS CIVIL WORK ~ 6%
- Boundary wall = 30%
- Line terracing/Roof top paver= 15%
- LOGO, Gardening & others = 4%
- GF BBC = 14%
- GF pavement & footpath dev = 10%
- Lintel, F/slab, drop wall, counter slab = 20%
- Cable tray = 1%
- Sanitary duct cover, ceiling etc= 4%
- Reception desk, letter box = 2%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ UTILITY CONNECTION & BILL ~ 3%
- DESA/DESCO = 35%
- TITAS = 20
- WASA = 15%
- Utility bills = 30%
TOTAL = 100% (৩% যেভাবে হবে।)

27/05/2023

➤ একটা বিল্ডিং এর সকল আইটেম মিলে ১০০% কিভাবে ভাগ করা হয়।
☞ উত্তরঃ
1. Structure = 35%
2. Brick work = 6%
3. Wood work = 5%
4. Metal work = 2%
5. Plambing and Sanitary = 6%
6. Electrical work = 7%
7. Plaster work = 4%
8. General Floor Tiles work = 6%
9. Toilet & Kit wall Tiles work = 3%
10. Aluminium work = 4%
11. EME(Lift,Generator,Substation)=10%
12. Paint work = 3%
13. Others civil work = 6%
14. Utility connection & Bill = 3%
Total = 100%
✪ STRUCTURE ~ 35%
- Footing & Column Padestal = 20%
- Grade Beam, UGWR top Slab = 5%
- GF Column, Stair etc = 4%
- 1st Floor Slab = 9%
- Typical Floor Column (5x3%) = 15%
- 2nd floor slab to roof slab (5x8) = 40%
- Roof top = 7%
TOTAL = 100% (৩৫% যেভাবে আসবে।)
#সিভিল_ইঞ্জিনিয়ারিং
✪ BRICK WORK ~ 6%
- GF Brick work = 6%
- 1st floor Brick work = 18%
- 2nd floor Brick work = 18%
- 3rd floor Brick work = 18%
- 4th floor Brick work = 18%
- 5th floor Brick work = 18%
-Roof Top Brick work = 4%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ WOOD WORK ~ 5%
- Door frame = 40%
- Main Door Shutter = 15%
- Partex Door Shutter = 35%
- Cat Door & Accessories = 10%
TOTAL = 100% (৫% যেভাবে হবে)
✪ METAL WORK ~ 2%
- Window grill = 55%
- Verandah Railling = 20%
- Stair Railling = 10%
- Main gate, Gen-Sub, safety grill = 15%
TOTAL = 100% (২% যেভাবে হবে।)
✪ PLAMBING & SANITARY WORK~ 6%
- uPVC vertical line thru duct = 25%
- GI line work = 30%
- Fixture & Fittings = 40%
- Ground Floor = 5%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ ELECTRICAL~ 7%
- Conduiting inside slab = 10%
- Conduiting on wall i/c MK box=15%
- Cabling work = 55%
- Switch-Socket = 20%
TOTAL = 100% (৭% যেভাবে হবে।)
✪ PLASTER ~ 4%
- Ceiling plaster = 20%
- Internal wall plaster = 50%
- Outside plaster/facing bricks = 30%
TOTAL = 100% (৪% যেভাবে হবে।)
✪ GENERAL FLOOR TILES ~ 6%
- General floor & Verandah = 75%
- Stair, typical lobby & lift wall = 20%
- GF lift lobby, wall, reception = 5%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ TOILET & KIT WALL TILES ~ 3%
- Bath wall = 60%
- Kitchen wall = 20%
- Bath floor = 9%
- Bath counter top = 4%
- Kitchen floor = 3%
- Kitchen counter top =4%
TOTAL = 100% (৩% যেভাবে হবে।)
✪ ALUMINIUM WORK ~ 4%
- Outer framing-window sliding= 40%
- Glass shutter-window sliding = 30%
- Verandah sliding = 20%
- Toilet high window = 5%
- Comnon area = 5%
TOTAL = 100% (৪% যেভাবে হবে।)
✪ EME ~ 10%
- Lift = 50%
- Generator = 25%
- Substation = 20%
- PABX, Fire extinguisher etc = 5%
TOTAL = 100% (১০% যেভাবে হবে।)
✪ PAINT WORK ~ 3%
- Upto putty = 40%
- Internal wall&ceiling 1st coat= 20%
- Internal wall&ceiling 2nd coat= 15%
- Outside paint/ceramic Tites = 25%
TOTAL = 100% (৩% যেভাবে হবে।)
সিভিল ইঞ্জিনিয়ারিং
✪ OTHERS CIVIL WORK ~ 6%
- Boundary wall = 30%
- Line terracing/Roof top paver= 15%
- LOGO, Gardening & others = 4%
- GF BBC = 14%
- GF pavement & footpath dev = 10%
- Lintel, F/slab, drop wall, counter slab = 20%
- Cable tray = 1%
- Sanitary duct cover, ceiling etc= 4%
- Reception desk, letter box = 2%
TOTAL = 100% (৬% যেভাবে হবে।)
✪ UTILITY CONNECTION & BILL ~ 3%
- DESA/DESCO = 35%
- TITAS = 20
- WASA = 15%
- Utility bills = 30%
TOTAL = 100% (৩% যেভাবে হবে।)