Negative Float:
this happens when the contractual project completion date is earlier than the calculated project completion date in the forward calculations.
In this case you should compress the schedule to match the contractual finish date.
Constraints:
- use constraints when activities must start or finish on a specific date. network logic alone cannot reflect all project situations.
- sometimes activity must be accomplished according to specific dates rather than on dates determined by other activities in the project.
القيود :
يجب أن نستخدم القيود في حالة وجوب بدء او انتهاء النشاط في تاريخ معين
حيث أن ال network diagram لن تقوم بهذا العمل
Float Or Slack Calculations In CPM method:
Total Float (TF):
the total float TF of an activity is the maximum time that activity can be delayed without causing delay in the final project completion.
Total Float (TF) = Late Finish (LF) - Early Start (ES) - Duration (D)
Free Float (FF):
FF is the maximum time activity may be delayed without affecting the start of the successor activities.
Free Float (FF)= Early Finish (EF)-Early Start (ES)- Duration (D)