BAM - Advanced Wellbeing Research Centre AWRC
BAM is developing the Advanced Wellbeing Research Centre in Sheffield. The £9 million new build will be comprised of pile foundations,
17/01/2019
Progress photos...
Roof installation ongoing - this is the first 2 layers on the roofing system for the tower building which involves the bitumen primer and the torch-applied bituminous air and vapour control layer.
Last structural topping pour to the upper floors completed Monday to the motion lab roof.
Hoist installation is ongoing and will be completed by end of play tomorrow.
SFS installation commenced to level 2 along GL 7 prior to the installation of the mass climbers.
Lightening protection tapes now installed to the building frame - from the pile cap foundations to the steelwork at ground floor and roof level. Further works involved with this is to be carried out once the roofs are completed.
Progress photos...
Roof installation ongoing - this is the first 2 layers on the roofing system for the tower building which involves the bitumen primer and the torch-applied bituminous air and vapour control layer.
Last structural topping pour to the upper floors completed Monday to the motion lab roof.
Hoist installation is ongoing and will be completed by end of play tomorrow.
SFS installation commenced to level 2 along GL 7 prior to the installation of the mass climbers.
Lightening protection tapes now installed to the building frame - from the pile cap foundations to the steelwork at ground floor and roof level. Further works involved with this is to be carried out once the roofs are completed.
18/12/2018
BAM have a great relationship with Sheffield and our last 5 years in the city has generated over 200 permenant jobs and more than 1000 apprenticeship weeks!
05/12/2018
Progress photos...
75mm fibre mesh concrete - structural topping pour now completed to all levels in phase 1 (GL 7a-9 / A-C1)
09/11/2018
More progress photos...
Phase 1 steelwork and pre-cast concrete planks now complete GL 7a-9 / A-C1.
Phase 2 steelwork and pre-cast concrete planks ongoing GL 7a-9 / C1-E1.
Scaffolders commenced on site this week installing edge protection and void protection for safe access to all levels.
Tarmac to be completed tomorrow to provide a firm platform for MEWP access around the building during construction.