Assembly work, new steam turbine 26MW progress ahead the Plan. Next milestone are installing of Reduction Gear & Moving the Existing Generator, Welcome 600ton Crawler Crane at the end of Feb.
02/01/2025
Ready for Installation, unloading completed, fabrication support work in progress, our best effort output for royalty Client.
19/11/2024
Construction progress for Waste Bunker and Boiler area of Chiangmai Waste to Energy 9.9MWe, this project will manage MSW for 200,000 tons/annual.
02/11/2024
Coming soon 26MW replacement project, FAT JAPAN.
11/10/2023
Thank you for giving us with the opportunity to proudly be a part of the challenging 26MWe steam turbine and generator replacement project.